1. |
Measure the pressure of high pressure line by
measuring voltage output between NO.1 and NO.2
terminals.

|
2. |
Inspect the voltage value whether it is
sufficient to be regular value or not.
Voltage = 0.00878835 * Pressure +
0.37081095 [PSIA]
| |
3. |
If the measured voltage value is not
specification, replace the A/C pressure
transducer |
1. |
Disconnect the negative (-) battery
terminal. |
2. |
Recover the refrigerant with a
recovery/charging station. |
3. |
Disconnect A/C pressure transducer connector
(3P) (A). |
4. |
Remove the A/C pressure
transducer(B).

Take care that liquid & suction pipe
are not
bent. | |
5. |
Installation is the reverse order of
removal.
TORQUE: 10~12N.m (1.0~1.2kgf.m,
7.4~8.8lbf.ft)
| | |